Indirect Costs Using a Costing Sheet in Microsoft Dynamics AX 2009
This document includes steps users can use to help understand how the Costing
Sheet works.
- Log into the Contoso Database or demo data for Microsoft Dynamics AX 2009.
- Create a new Indirect Cost group called Lab_OH with a Name of Labor
Overhead.
- Go to Inventory Management, choose Setup, choose Bills of materials, choose
Cost groups.
- Create a new cost group called Lab_OH
- Enter Labor Overhead in the Name field
- Choose Indirect in the Cost group type field
- Save the new Cost group
- Go to the Costing Sheet
- Go to Inventory Management, choose Bills of Materials, choose Costing sheet
setup
- Create a new Total Node Called Overheads
- Go to Inventory management, choose setup, choose Costing sheet setup
- Right-click the COGM node and then click Create
- Select Total in the Node Type field and click OK
- With the new Total node selected, on the Edit tab, mark the Header and Total
checkboxes in the Setup field group
- Create a new Cost group node
- Right click the Total Node you just created and choose Create
- Choose Cost Group in the Select node type field.
- Call the new Cost Group Labor Overhead
- Assign the Labor Overhead Cost group you created in step 2 to this node
- On the Edit tab in the Setup field group, choose the Lab_OH Cost
group
- Create a Surcharge Node
- Under the Costing group Node created in step 5, create a new Surcharge Node
- Right-click on Labor Overhead and choose Create
- Choose Surcharge in the Select node type field
- On the General tab, choose Total in the Subtype field
- On the Calculation Tab choose Manufacturing in the Code field
- Under the Surcharge section at the bottom of the form, choose a Version in
the Version field, choose a Site in the Site field and enter 50.00 in the
Percent field
- Save the Surcharge
- Click on the Activate button to Activate the Surcharge
- Under Posting Configure the WIP and costing accounts
- Save the Costing sheet by choosing the Save button
- Create a new production order for the Item 1171
- Create an order for 1 unit
- Estimate the order
- Go to Inquiries, choose Price Calculation, then select Costing Sheet
- Please note when you go to Overhead, then choose Labor overhead that the
value is 50% of the Manufacturing cost, in this case for a production for 1
unit, this cost is going to be 3.33
- Delete the Surcharge node and create a Rate node instead.
- Highlight the Surcharge node and choose the delete icon.
- Right-click on the Labor Overhead node and choose Create
- Choose Rate in the Select node type field
- Choose OK
- On the General tab, choose Process in the Subtype field
- On the Calculation tab, choose Manufacturing in the Code field
- On the Posting tab, choose the WIP and Indirect posting accounts
- In the Rate section at the bottom of the form
- Choose a version in the Version field
- Choose a Site in the Site field
- Enter 50.00 in the Amount field
- Save the node
- Choose the Activate button
- Save the Costing Sheet
- Create a new production order for the Item 1171
- Estimate the production order
- Go to Go to Inquiries, then choose Price Calculation
- Please note that the calculated overhead is $50*Process time for each
operation with a cost category related to the Manufacturing Node. In this case
it calculates out to be 19.64
- Change the subtype of the Rate node to Quantity for 1 unit
- On the General tab, choose Quantity in the Subtype field
- Save the Costing Sheet
- Create a new production order for the Item 1171
- Estimate the production order for the Item 1171
- Go to Inquiries, then choose Price Calculation
- Note that the calculated Labor Overhead is $50*Quantity produced in each
operation. In this case is going to be 100
No comments: